Required Signed POs

<< Click to Display Table of Contents >>

You are here:  Greenlight Compliance Manager™ > Manage Greenlight™ > Configuration > Configuring Settings >

Required Signed POs

Greenlight CM™ allows you to track that executed purchase orders are returned by vendors and subcontractors.

 

1.From the ribbon toolbar, click Greenlight.

2.Click Manage Greenlight, GreenlightManageGreenlighticon-mh.
 
The main screen displays with the Users tab active:
 
GreenlightManageGreenlightmainscreen-mh
 

3.Click the Configuration tab.
 
The following screen displays:
 
GreenlightManageGreenlightmainscreenConfigurationtab-mh
 

4.In the Configuration Settings grid, locate the Require Signed POs check box.

5.Click the check box to enter a checkmark and turn on the requirement.